
Vol 20, No. 2 August 2001
Inside This Edition:
Prompt Payment Bill Passed * President’s Message * Court
Decision Time to Complete * Emergency Contract Law
Extended * New Members * Why
Belong to NESCA
__________________________
PROMPT
PAYMENT BILL PASSED IN LEGISLATURE (Go Top)
Legislation which would mandate prompt
payment protections for contractors, subcontractors and suppliers on private
construction projects has passed in both houses of the NYS Legislature and will
be sent to Governor Pataki for his consideration. This bill (S4318B/A7698B), sponsored by Senator Guy Velella (R-
Westchester) and Assemblyman Peter Rivera (D-Bronx), passed in the Senate on
June 21st and in the Assembly on June 25th.
It would establish prompt payment standards for most private construction
projects exceeding $125,000. The bill
does not apply to public works projects nor developments of ten or less
single-family or two-family homes. New
York State has a long-standing law covering prompt payment on public works
projects. Specifically, the legislation
would require the following:
*
Progress payments shall be made by the owner every 30 days on all contracts
with a duration of 60 days or more.
* The
owner must make progress payments within 7 days after the date a billing from
the contractor is approved.
* A
billing is deemed approved 14 days after the owner receives it unless before
the 14-day period has expired, a written statement is provided to the
contractor detailing those items in the billing that are not approved.
* An
owner may decline to approve a billing for a variety of reasons including: unsatisfactory job progress; defective work
or materials; disputed work or materials; failure to comply with other material
provisions of the contract; failure by the contractor to make timely payments
for labor including collectively bargained fringe benefit contributions and
payroll taxes and insurance; damage to the owner; and reasonable evidence that
the contract cannot be completed for the unpaid balance of the contract sum.
* Final
payment must be made by the owner within 7 days of the owner's approval of the
work.
*
Failure by the owner to meet these payment standards will result in a 1 1/2 per
month interest penalty.
* Upon
a written request made by a subcontractor, the owner must notify the sub within
5 days of making progress payments to the contractor.
* The
contractor must pay subcontractors and suppliers within 7 days of receipt of
payment by the owner.
* A
billing by a subcontractor to the contractor shall be deemed approved 21 days
after the contractor receives the billing unless before the 21-day period has
expired a written statement is provided to the subcontractor detailing those
items in the billing that are not approved.
* A
contractor may suspend performance or terminate the contract for nonpayment
after providing the owner with a 7-day written notice.
* A
subcontractor may suspend performance or terminate the subcontract for
nonpayment after providing the contractor with a 3-day written notice.
In addition to the prompt payment
protections, this legislation would also make certain provisions of
construction contracts void and unenforceable in New York State. Specifically, the bill would:
*
Render void contract provisions which make the contract subject to the laws of
another state or which requires litigation, arbitration or other dispute
resolution proceeding to be conducted in another state.
*
Render void contract provisions which state that a party to the contract cannot
suspend performance or terminate the contract if another party to the contract
fails to make prompt payments.
*
Render void contract provisions which state that payment by an owner to a
contractor is a condition precedent for payment by a contractor to a
subcontractor or supplier.
Not so surprisingly, the General Building
Contractors of NYS has come out in opposition to this bill. Apparently, the general contracting
community is not in favor of prompt payment.
To counteract this opposition, NESCA members are urged to fax letters of
support for this legislation to Governor Pataki at (518) 474-1513.
There
will be no NESCA Membership Meetings during July and August. The next Membership Meeting will be held on
September 13, 2001

With baseball's All-Star game now but a
memory, we enter the dog days of summer and await the inevitable fade of the
Boston Red Sox. As engaging as this
team may be, most Red Sox fans are resigned to accept the certainty of the
"Curse of Babe Ruth", and with pained expressions will likely have to
endure yet another title run by the Yankees.
While a late summer collapse is almost inescapable for the Red Sox,
NESCA's own team of board and committee members are hard at work to guarantee
yet another successful year for your association.
The Program Committee, chaired by Jim
Elacqua with AFSCO Fence Supply Co., Inc., recently met to develop a lineup of
speakers and topics for NESCA's 2001-02 membership meetings. Coming off the popularity and success of
last year's "mini-seminar" format, this committee is poised to
provide members with another year of valuable and interesting dinner meeting
programs. And don't forget -- our first
membership meeting of the year will be held on September 13th at the Century House
in Latham.
Also coming to bat in July was the Golf
Committee, chaired by Brian Carmer with Stone Bridge Iron & Steel, Inc.
This committee met to prepare for NESCA's very popular Annual Golf Outing, to
be held on September 10th at McGregor Links Country Club in Saratoga. Whether you're a scratch golfer or a hacker,
all are welcome at this event. Just be
sure to sign up early because we generally sell-out the Golf Outing pretty
quickly once the registration forms are mailed out to the membership.
In addition, Chairman Dick McNitt with
KAMCO Supply Corp. has scheduled a Suppliers Committee meeting for August 14th
to discuss details related to NESCA's Annual Trade Show to be held this year on
October 11th at the Century House. I have no doubts the committee will hit
another home run with this year's Trade Show, but if you have any fresh ideas
I'm sure Dick would welcome your input. And finally, hitting cleanup, the
NESCA/ECA/GBC Joint Educational Partnership will meet in August to address
ideas for the educational seminars and courses that will be offered to members
during the coming year. If your
business has particular educational/training needs you wish to see tackled by
the Educational Partnership this year, please contact the NESCA office with
your ideas.
All members have been mailed information
about the Empire State Subcontractors Association (ESSA) Annual Conference
which will be held September 14-15, 2001 at the Turning Stone Casino Resort.
The Conference is open to all members from each of ESSA's five affiliated
chapters in Buffalo, Rochester, Syracuse, Albany and New York City. ESSA has
put together a very nice combination of educational programs and social
activities, and members will be given the opportunity to provide input
regarding issues to be adopted by ESSA as part of its 2002 legislative program.
But maybe most of all, the Conference will provide members with a great
opportunity to network with other subcontractors and suppliers from around the
State who face -- and deal with -- the very same business issues you do. I encourage all members to register for the
ESSA Annual Conference.
Robert
H. Kind
President
CONTRACTOR ALLOWED REASONABLE TIME
TO COMPLETE JOB (Go Top)
In a recent case before the Appellate Division,
Second Department (Teramo & Co., Inc. v. O'Brien-Sheipe Funeral Home, Inc.,
May 29, 2001) the Court held where a contract fails to state a date for the
completion of a construction project, a reasonable time is implied. In the instant case, the defendant hired the
plaintiff to construct an addition to it's funeral home. the parties contract did no specify a date
for completion of the proposed work nor did it include a "time is of the
essence" provision. The project
was substantially completed by the plaintiff who commenced this action to
recover the outstanding balance. The
defendant asserted counterclaims seeking damages for business allegedly lost
due to delay in the construction.
The Appellate Court, in reversing the
lower court's decision stated "what constitutes a reasonable time for
performance of a contract depends upon the facts and circumstances of the
particular case, including the subject matter of the contract, the situation of
the parties, their intention, what they contemplated at the time the contract
was made, and the circumstances surrounding performance."
Once again, this case reminds us that the
completion date is an integral part of the construction contract and where
there is a "time is of the essence" clause contained within the
contract, failure to meet the construction schedule or to complete the project
on the completion date would constitute a breach of the contract by the
contractor subjecting him to a claim for damages by the owner. Where, as in this case, there is no completion
date in the contract, the court will review the facts of the case and the
above-mentioned circumstances to determine what constitutes a reasonable time
to complete the job.
Contractors and owners would be prudent in
assuring that the construction contract contains a completion date and, if
intended, a "time is of the essence" provision.
Terence
J. Burke, Esq.
NESCA
Legal Counsel
EMERGENCY CONTRACT LAW EXTENDED FOR
2 MORE YEARS (Go Top)
Governor Pataki has signed legislation
extending the State's "emergency contract" law for another two years,
until June 2003. This extension will
allow the Office of General Services to continue awarding emergency contracts
in amounts up to $200,000. Since 1993,
the Public Buildings Law has authorized OGS to let contracts of up to $200,000
to respond to construction emergencies involving a pressing necessity for
immediate repair, reconstruction or maintenance of State facilities. Such contracts may be let without formal
competitive bidding, but are required to be based on the solicitation of oral
bids by at least three contractors. The
$200,000 limit was authorized for an initial 2-year period in 1993, and was
extended for additional 2-year periods in 1995, 1997 and 1999 prior to this
latest extension. Absent these
extensions, the monetary limit for emergency contracts would revert back to the
old $40,000 value.
NESCA members had often experienced
payment delays in the performance of emergency contracts for the State which
had been averaging 115 days to process emergency contract awards for projects
which typically had durations of only a few weeks. As such, the 1997 extension included a requirement that the
Office of General Services, in consultation with the Division of the Budget,
general contractors and specialty trade contractors, study and evaluate the
procedures employed in the administration of emergency contracts. The charge was to identify problems and
issues under the existing laws and regulations, including the issue of timely
payment for services rendered, and to make recommendations for changes in law
or regulation to improve the process.
NESCA was invited to participate in this process, and after studying the
issue it was determined that a number of OGS administrative procedures
contributed to such delays, but the primary cause of delays in emergency
contract payments was waiting for funding from client agencies. To improve the timeliness of emergency
contract payments, several internal procedures were modified at OGS and an
administrative process was developed between OGS and client agencies to
expedite the funding of emergency contract work.
NESCA will continue to monitor payment
problems associated with emergency contracts.
Members who experience specific problems should contact the NESCA
office.
Harleysville Surety
910 Perinton Hills Office Park
Rochester, NY 14450
(716) 223-7330; Fax (716) 223-8035
Contact: Harry Wolf
Encompass Mechanical Services
20 Loudonville Road
Albany, NY 12204
(518) 432-9023; Fax (518) 432-9680
Contacts: Dave Legge, Ray Gargett
WHY DO YOU BELONG TO NESCA? (Go Top)
Free
Lien Filing Service
- One of NESCA's most important and most utilized services for over 20
years. Each year NESCA files 250-300
liens for our members on both public and private construction projects.
Workers'
Compensation Safety Group
- Offered through Allied Safety Services, Inc., NESCA members may take
advantage of the safety group concept to reduce your premiums and have access
to professional loss control and claims management services.
Legislative
Program - Through
NESCA's state affiliate (ESSA), members are provided with advocacy in the NYS
Legislature, the Courts and in State Agencies.
ESSA has successfully authored 31 laws which benefit subcontractors and
suppliers statewide.
Statutory
DBL Program -
Another popular advantage to membership is NESCA's Group Statutory DBL
Program. This program is administered
by Corporate Benefit Planning and offers low monthly rates to help members save
on their DBL costs.
Employee
Assistance Program
- In this age of motor carrier safety requirements, DOT checkpoints and drug
& alcohol testing regulations, members may take advantage of our full-service
EAP developed for NESCA by Human Resource Associates for an extremely low
annual fee of $25 per employee.
Group
Section 125 Program
- This free program, administered by Corporate Benefit Planning, allows the employer-paid
portion of health insurance premiums, dental expenses, eye care expenses and
other qualified health-related expenses to be made on a pre-tax basis saving
money for both employers and employees.
Educational
Seminars - NESCA
has joined with the General Building Contractors of NYS and Eastern Contractors
Association in an educational partnership to provide members a vast variety of
educational programs, from 3-hour management seminars......to superintendent
training courses..........to OSHA 10-hour and 30-hour training programs.
Monthly
Newsletter - NESCA
members are kept updated on industry developments and changes through our
monthly Newsletter and other special bulletins.
Annual
Trade Show - NESCA's
Annual Trade Show provides members the opportunity to display their products
and services to over 500 subcontractors, general contractors, architects,
engineers and other building professionals.
Individual
Assistance -
NESCA's full-time professional staff is on hand to assist members with a wide
variety of business and construction-related matters such as: payment
assistance; contract assistance; assistance with OSHA regulations; affirmative
action; prevailing wage compliance; and a vast number of state and federal laws
and regulations which impact on subcontractors and suppliers.